The city is being asked for $2.1M more (plus $900K) in ARPA money to finish 65 affordable units on the top five floors of the historic Lee Plaza building — floors originally planned as market rate. Total phase-two cost is $22M with 45-year affordability commitments.

At a glance

Total mentions
1
Last 30 days
0

Last discussed Jun 24, 2026.

Impact analysis

💰Financial impact

The city's share is $3M of a $22M phase; all ARPA money must be spent by the end of 2026.

✅Who benefits

182 future households, including extremely low-income seniors on the first ten floors and 65 more affordable units upstairs.

⚠️Who could be affected

Some members questioned whether the city gets enough return after being told earlier phases would include market-rate units.

Mentions & discussions (1)

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Detroit

What the council decided, in plain English — one email a week.

Also follow nearby cities

Free. Unsubscribe with one click any time. We never sell your email.