DWSD finances and the GLWA lease
The Great Lakes Water Authority's new report warns Michigan's water systems urgently need investment. Council President Tate asked staff to review it — likely a prelude to bigger water-rate and infrastructure debates.
Private Sewer Repair Program Phase 2
A $250,000 federal disaster-recovery contract would pay for basement cleaning/sanitizing and HVAC repair or replacement for residents whose basements flooded — part of the ongoing sewer backup response.
DDOT bus tires, DEF fluid, and inventory audit contracts
New city-funded contracts would buy bus tires and tire services, increase DEF fluid funding, and audit DDOT's inventory — the nuts and bolts that keep buses running on time.
ADA paratransit grant increase
The committee will consider accepting an increased appropriation for the Section 5310 ADA paratransit grant, expanding support for door-to-door service for seniors and riders with disabilities.
$18 million DWSD water/sewer inspection contract
A fully federally funded contract with DLZ Michigan will provide inspection and testing for DWSD's lead line and sewer work across all seven districts, helping roughly 9,000 homes.
DWSD and Great Lakes Water Authority finances
A report reviews how GLWA was created, its relationship with DWSD, and both agencies' audited financials — with questions raised about the lease agreement and its terms.
Cable and Telecommunications Franchise Agreements
The city is renewing its 10-year video service franchise agreement with DIRECTV, ensuring continued municipal revenue and public education channel access.
DTE rate increase public hearings
The council formally asked the Michigan Public Service Commission to hold public hearings in Detroit before deciding any DTE gas or electric rate hike — a shot at giving residents a voice in utility bills.
$184 Million Alley Sewer Repair Program
Two of the first contracts — $5M with DMC Consultants and $25M with Precision Infrastructure — were recommended. DWSD will fix failing private sewer connections causing sinkholes and restore affected alley surfaces, with outreach before work in all seven districts.
Water affordability and H2O Lifeline program terms
A resident approved for the $34/month Lifeline water program says she got past-due bills she never expected and no written explanation. Pro Tem Young confirmed a DWSD discussion is being scheduled.
$50 Million in Alley Sewer Repairs From Disaster Recovery Funds
Two $25 million contracts — funded entirely by 2023 flood disaster-recovery money — will inspect, rehab, and replace alley sewers citywide. Both advanced to full Council.
DTE Substation Power Outage in District 2
An underground cable failure at a DTE substation left much of District 2 without power on an extreme heat day. DTE is deploying 14 diesel generators to eight locations, with community vans at rec centers, and the chair's office is pushing for a van at Northwest Activity Center.
Infrastructure and Water Main Repairs
The committee reviewed major contracts for hard surface restoration and water main emergency repairs following an unusually harsh winter that caused hundreds of water main breaks. Officials discussed long-term infrastructure replacement plans.
DWSD water and sewer contracts
Two bond-funded contracts totaling about $41.5 million would fund citywide emergency sewer repairs and replace five miles of water main in Palmer Park, Denby and Mapleridge. Both were recommended for approval.
Basement back-up protection program
A time-only extension keeps contractor LGC Global available in case more ARPA funds are found for basement flooding protection.
GLWA pump station rezoning and 2021 flood prevention
The GLWA rezoning for a new pump station would help prevent a repeat of the 2021 basement flooding that hit thousands of Eastside homes, but neighbors near the site object to dust, disruption, and lack of home-repair support. The committee held the item a week to allow more community conversation.
Stormwater drainage fee
Multiple callers blasted the drainage fee as ruled illegal in court yet still being charged — council did not directly respond.
GLWA Lease and Water Affordability
Residents pressed the committee on the regional water authority lease signed under emergency management — a study says the city should get about $218 million a year but receives far less — and asked council to fund DWSD water assistance and codify a water affordability ordinance.
GLWA Frood/Conner pump station rezoning in Jefferson Chalmers
The rezoning lets GLWA's pump station site be redeveloped, but the chair says neighbors still want commitments on basement backup protection, upsized drains and federal BRIC grant money before fully supporting it.
Public lighting department decommissioning
Pro Tem Young pressed for an end date on the PLD decommissioning, calling it a farewell tour that never ends, as another $4.5 million contract came forward. Staff said the work largely pays for itself through scrapped copper but couldn't give a final date.
Sewer repair grant administration (HRD vs. DWSD)
A resident asked why sewer repair grants run through the housing department instead of the water department; HRD explained it administers all CDBG dollars, including $97 million in 2021 flood recovery funds, in partnership with DWSD.
Sewer backup and seawall recovery programs
The private sewer repair program still has funding across 97 neighborhoods for 2021 backup victims, a $356 million CDBG-DR grant will fund alley sewer repairs affecting 10,000–15,000 households, and a $1 million seawall pilot is being scoped for Jefferson Chalmers.
Water main breaks and frozen hydrants
DWSD is repairing roughly as many main breaks daily as it closes, with 15-30 burst meters per day and under 1% of 30,000 hydrants frozen. Members asked for better council notification, bottled water delivery, and hydrant freeze-prevention ideas.